No.DescriptionQuantityUnitRateAmount
1FE-500 Reinforcement Bar85000kg403400000
2Cement12300begs2753382500
3Natural Sand400brass67862714400
4Crushed sand165brass1944.5320842.5
5Coursed Aggregate 350brass2500875000
6Burnt Bricks230000nos81840000
7Vitrified Tiles22200sqft37821400
8Antiskid Tiles2100sqft3267200
9Cota stone for staircase1915sqft3872770
10Dado Tiles (for toilet )6500sqft28182000
11Dado Tiles (for ward )19000sqft30570000
12Flush Door with concrete frame3635sqft220799700
13Wooden Door Partly Glazed170sqft337.757409
14Sliding Window3640sqft221.75807170
15Aluminium Ventilator 420sqft17573500
16Structural Glazing650sqft246159900
17M.S. Grill3825sqft94.5361462.5
18S.S. Railing1360rft319.85435000
19Colouring Material lumsum 1150000
20Plumbing Material lumsum 1200000
21Electrification Material lumsum 1350000
22Construction Chemical lumsum 150000
23Construction Equipment Rent, Maintains And Transport lumsum 325000
24Excavation and Filling Charges lumsum 300000
25Elevation Treatment And Beautification lumsum 500000
26Contingencies lumsum 1000000